CORRECTION; PDE Monthly Report Distribution Status
The distribution of the February 2018 PDE month-end reports is complete. The table below provides the dates of distribution for each report and Benefit Year.
Benefit Year | Report Name | Date of Distribution | Report Sequence #* |
---|---|---|---|
2018 | Plan to Plan (P2P) | 03/09/2018 | 2018002 |
2018 | Cumulative Beneficiary | 03/10/2018 | 2018002 |
2017 | Plan to Plan (P2P) | 03/10/2018 | 2017014 |
2017 | Cumulative Beneficiary | 03/11/2018 | 2017014 |
2016 | Cumulative Beneficiary | 03/11/2018 | 2016026 |
2015 | Cumulative Beneficiary | 03/11/2018 | 2015038 |
2014 | Cumulative Beneficiary | 03/11/2018 | 2014050 |
2013 | Cumulative Beneficiary | 03/11/2018 | 2013062 |
2012 | Cumulative Beneficiary | 03/11/2018 | 2012074 |
2011 | Cumulative Beneficiary | 03/12/2018 | 2011086 |
In the event you have questions, please contact CSSC Operations at 1-877-534-2772 or by email at csscoperations@palmettogba.com.